  1. A contractor was engaged to construct a road in 16 days. After working for 12 days with 20 labours it was found that only 5/8 th of the road had been constructed. To complete the work in stipulated time the number of extra labours required is :
    1. 18
    2. 10
    3. 12
    4. 16
Correct Option: D

Using Rule 1,
Remaining work

= 1 -
5
=
3
;
88

Remaining time = 4 days
M1D1
=
M2D2
W1W2

=
20 × 12
=
M2 × 4
5/83/8

=
20 × 12
=
M2 × 4
53

⇒ 4 × 12 =
M2 × 4
3

⇒ M2 = 12 × 3 = 36
∴ Number of additional workers
= 36 – 20 = 16