  1. A and B together can complete a work in 24 days. B alone does 1/3 rd part of this work in 12 days. How many days will A alone take to complete the remaining work?
    1. 24 days
    2. 36 days
    3. 48 days
    4. 72 days
Correct Option: C

∵ B completes
1
work in 12 days.
3

∴ B will complete 1 work in 12 × 3 = 36 days.
∴ B’s 1 day’s work =
1
36

(A + B)’s 1 day’s work =
1
24

∴ A’s 1 day’s work =
1
-
1
2436

=
3 - 2
=
1
7272

∴ Time taken by A in doing 1 work = 72 days
Remaining work = 1 –
1
=
2
33

∴ Time taken by A in doing
2
work =
2
× 72 = 48 days
33