  1. P can do 1/4 th of work in 10 days, Q can do 40% of work in 40 days and R can do 1/3 rd of work in 13 days. Who will complete the work first?
    1. P
    2. Q
    3. R
    4. Both P and R
Correct Option: C

∵ P does 1/4 th work in 10 days.
∴ P will do 1 work in 10 × 4 = 40 days
∵ Q, does 40% part of work in 40 days
∴ Q will do 100% work in

40 × 100
= 100 days
40

∵ R, does
1
rd work in 13 days.
3

∴ R will do 1 work in 13 × 3 = 39 days