A can do a certain job in 12 days. B is 60% more efficient than A. To do the same job B alone would take :
-
-
7 1 days 2 - 8 days
- 10 days
- 7 days
-
Correct Option: A
Time taken by B
= 12 × | = | = 7 | ||||
160 | 2 | 2 |
Aliter : Using Rule 17,
Here, x = 12, R = 60%
Time taken by B
= x × | days | 100 + R |
= 12 × | days | 160 |
= | = 7 | days | ||
2 | 2 |