  1. 10 men working 6 hours a day can complete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days ?
    1. 6 days
    2. 10 days
    3. 12 days
    4. 15 days
Correct Option: A

Using Rule 1,

where, x is working hrs/days

15 : 10
: : 6 : x
12 : 18

⇒ 15 × 12 × x = 10 × 18 × 6
∴ x =
10 × 18 × 6
= 6 hours
15 × 12