  1. Seventy-five men are employed to lay down a railway line in 3 months. Due to certain emergency conditions, the work was to be finished in 18 days. How many more men should be employed to complete the work in the desired time ?
    1. 300
    2. 325
    3. 350
    4. 375
Correct Option: A

Using Rule 1,
M1D1 = M2D2
⇒ 75 × 90 = M2 × 18

⇒ M2 =
75 × 90
= 375
18

7there4; Number of additional men
= 375 – 75 = 300