A can do a piece of work in 60 days. He works for 15 days and then B alone finishes the remaining work in 30 days. The two together can finish the work in
-
- 24 days
- 25 days
- 30 days
- 32 days
Correct Option: A
Work done by A in 15 days
= | × 15 = | |||
60 | 4 |
Remaining work
= | 1 - | = | ||||
4 | 4 |
Now, 3/4 work is done by B in 30 days
Whole work will be done by B in
= | = 40 days | 3 |
A’s 1 day’s work = | and B’s 1 day’s work | 60 |
= | 40 |
(A + B)’s 1 day’s work
= | + | = | = | |||||
60 | 40 | 120 | 24 |
Hence, both will finish the work in 24 days