  1. A and B together can do a work in 8 days, B and C together in 6 days while C and A together in 10 days, if they all work together, the work will be completed in :
    1. 3
      3
      days
      4
    2. 3
      3
      days
      7
    3. 5
      5
      days
      47
    4. 4
      4
      days
      9
Correct Option: C

(A + B)'s 1 day's work =
1
.....(i)
8

(B + C)'s 1 day's work =
1
.....(ii)
6

(C + A)'s 1 day's work =
1
.....(iii)
10

On adding all three equations ,
2(A + B + C)'s 1 day's work =
1
+
1
+
1
8610

2(A + B + C)'s 1 day's work =
15 + 20 + 12
=
47
120120

⇒ (A + B + C)'s 1 day’s work =
47
240

∴ (A + B + C) together will complete the work in
240
= 5
5
days.
4747

Second method to solve this question ,
Here , x = 8 , y = 6 , z = 10
Time taken =
2xyz
xy + yz + zx

Time taken =
2 × 8 × 6 × 10
8 × 6 + 6 × 10 + 10 × 8

Time taken =
960
48 + 60 + 80

Time taken =
960
188

Time taken =
240
= 5
5
days.
4747