  1. X can do a work in 16 days. In how many days will the work be completed by Y, if the efficiency of Y is 60% more than that of X ?
    1. 10 days
    2. 12 days
    3. 25 days
    4. 30 days
Correct Option: A

Ratio of time taken by X
and Y = 160 : 100 = 16 : 1
Suppose Y takes y days to the work.
Then, 1.6 : 1 = 16 : y
∴ y = (16 x 1)/1.6 = 10 days