  1. A can do a piece of work in 10 days, while B can do it in 6 days. B worked at it for 4 days. How long will A take to finish the remaining work ?
    1. 31/3 days
    2. 32/3 days
    3. 32/5 days
    4. 35/7
Correct Option: A

B's 4 days work = (1/6) x 4 = 2/3
∴ Remaining work = 1 - (2/3) = 1/3
A's 1 day's work = 1/10
∴ 1/3 work is finished by A in
(10 x 1/3) = 31/3 days