Home » Aptitude » Time and Work » Question
  1. 45 people take 18 days to dig a pond. If the pond would have to be dug in 15 days, then the number of people to the employed will be ?
    1. 50
    2. 54
    3. 60
    4. 72
Correct Option: B

Given, M1 = 45, D1 = 18, M2 = ? , D2 = 15
By using the formula,
M1D1 = M2D2
∴ M2 = M1D1/D2
⇒ M2 = (45 x 18)/15 = 3 x 18
⇒ M2 = 54



Your comments will be displayed only after manual approval.