If 12 man or 18 women can do piece of work in 14 days. How long will 8 men and 16 women take to finish the work?
-
- 9 days
- 12 days
- 13 days
- 10 days
Correct Option: A
12 men =18 women
⇒ 1 man = 18/12 women
⇒ 8 men = 18/12 x 8 = 12 women
Given m1 = 18 M2 = 12 +16 = 28,
D1 , D2 = ? and W1 = W2 = 1
According to the formula
M1D1W2 = M2D2W1
⇒ 18 x14 x1= 28 x D2 x1
∴ D2 = (18 x 14)/28 = 9 days