  1. If 15 men can prepare 12 toys working 5 h per day in 16 days, then in how many days can 10 men prepare 15 toys working 8 h per day ?
    1. 182/3 days
    2. 183/4 days
    3. 184/5 days
    4. 185/7 days
Correct Option: B

Using formula M1D1T1W1 = M2D2T2W2
M1 = 15, M2 = 10, D1 = 16, D2 = ?
T1 = 5, T2 = 8, W1 = 15, W2 = 12
Now, 15 x 16 x 5 x 15 = 10 x D2 x 8 x 12
D2 = (15 x 16 x 5 x 15)/(10 x 8 x 12)
= (15 x 15)/12 = 75/4 = 183/4 days