-
A, B and C working in a garment manufacturing company can do the same assignment in 24, 6 and 12 days, respectively. Working together the assignment will be complete in how many days ?
-
- 33/7 days
- 43/7 days
- 4 days
- 3 days
Correct Option: A
(A + B + C)' S 1 day's work = (1/24) + (1/6) + (1/12) = 7/24
∴ (A + B + C) can do the entire work in = 24/7
= 33/7 days