Home » Aptitude » Time and Work » Question
  1. A can do a piece of work in 24 days. If B is 60% more efficient than A, then the number of days required by B to do the same piece of work is ?
    1. 10
    2. 15
    3. 12
    4. 9.6
Correct Option: B

Efficiency of A = 4.16%
Efficiency of B = 1.6 x 4.16 = 6.66%

∴ Number of days required by B = 100/6.66 = 15 days