  1. A can finish a piece of work in 12 days while B can do it in 15 days. If both work at it together, what time will they take to do the work?
    1. 6 days
    2. 8 days
    3. 62/3 days
    4. 101/15 days
Correct Option: C

Efficiency of A = 100/12 = 8.33%
Efficiency of B = 100/15 = 6.66%
Combined efficiency of A and B = 8.33 + 6.66 = 15%
Number of days taken by A and B, when worked together = 100/15
= 62/3 days