A can do a certain job in 25 days which B alone can do in 20 days. A started the work and was joined by B after 10 days. The work lasted for ?
-
- 121/2
- 142/9
- 15 days
- 162/3
Correct Option: D
A's 10 day's work = 10 x (1/25) = 2/5
Remaining work = 1 - 2/5 = 3/5
Work was done by (A + B) in 1 day = (1/25 + 1/20) = 9/100
∴ 3/5 work was done by (A + B) in (100/9 x 3/5) = 20/3 days
Hence, the work lasted for (10 + 62/3) = 162/3 days.