  1. A can do a piece of work in 30 days while B can do it in 40 days. In how many days can A and B working together do it ?
    1. 70 days
    2. 423/4 days
    3. 271/7 days
    4. 171/7 days
Correct Option: D

(A + B)'s 1 day's work = (1/30 + 1/40) = 7/120

∴ Time taken by both to finish the work = 120/7days = 171/7 days