Clocks and Calendars


  1. A watch which gains uniformly, is 5 min slow at 7 o'clock in the morning on Sunday and it is 5 min 48 s fast at 7 pm on following Sunday. Which day was it correct ?











  1. View Hint View Answer Discuss in Forum

    Time from 7 am on Sunday to 7 pm on following Sunday
    = 7 days 12 h = 180 h
    ∴ Watch gains (5 + 54/5) min or 54/5 in 180 h.
    Now, 54/5 min are gained in 180 h.
    ∴ 5 min gained in (180 x 5/54 x 5) h
    = 83 h 20 min.

    Correct Option: D

    Time from 7 am on Sunday to 7 pm on following Sunday
    = 7 days 12 h = 180 h
    ∴ Watch gains (5 + 54/5) min or 54/5 in 180 h.
    Now, 54/5 min are gained in 180 h.
    ∴ 5 min gained in (180 x 5/54 x 5) h = 83 h 20 min.
    = 3 days 11 h and 20 min

    ∴ Watch is correct after 3 days 11 h and 20 min after 7 am of Sunday.
    ∴ It will be correct at 20 min past 6 pm on Wednesday.


  1. On the 6 March, 2005, Monday falls. What was the day of the week on 7th March 2004 ?











  1. View Hint View Answer Discuss in Forum

    6th March 2005 = Monday.
    Then, 6th March 2004 = Monday - 1 day = Sunday
    [ ∵ 2004 is a leap year but it does not cross 29th February of 2004, so only 1 is taken as odd day. ]

    Correct Option: B

    6th March 2005 = Monday.
    Then, 6th March 2004 = Monday - 1 day = Sunday
    [ ∵ 2004 is a leap year but it does not cross 29th February of 2004, so only 1 is taken as odd day. ]

    6th March 2004 = Sunday
    7th march 2004 = Monday.



  1. The year next to 1991 having the same calender as that of 1990 is ?









  1. View Hint View Answer Discuss in Forum

    We go on counting the odd day from 1991 onwards till the sum is divisible by 7 .

    Correct Option: C

    We go on counting the odd day from 1991 onwards till the sum is divisible by 7 . The number of such days are 14 up to the year 2001. So, the calendar for 1991 will be repeated in the year 2002.


  1. What was the day of the week on 17th July, 1776 ?











  1. View Hint View Answer Discuss in Forum

    Period upto 17th July, 1776 = 1775 yr + Period from 1st January 1776 to 17th July 1776

    Counting of odd days
    In 1600 yr = 0
    In 100 yr = 5
    75 yr = 18 leap years + 57 ordinary years = (18 x 2 + 57 x 1) odd days
    = 93 odd days
    = 13 weeks + 2 days
    = 2 odd days

    ∴ 1775 yr have(0 + 5 + 2) odd days
    = 7 odd days = 1 week + 0 odd day
    = 0 odd day

    Number of days between 1.1.1776 to 17.7.1776
    January + February + March + April + May + June + July
    31 + 29 + 31 + 30 + 31 + 30 + 17 = 199 days = 28 weeks + 3 odd days

    Correct Option: A

    Period upto 17th July, 1776 = 1775 yr + Period from 1st January 1776 to 17th July 1776

    Counting of odd days
    In 1600 yr = 0
    In 100 yr = 5
    75 yr = 18 leap years + 57 ordinary years = (18 x 2 + 57 x 1) odd days
    = 93 odd days
    = 13 weeks + 2 days
    = 2 odd days

    ∴ 1775 yr have(0 + 5 + 2) odd days
    = 7 odd days = 1 week + 0 odd day
    = 0 odd day

    Number of days between 1.1.1776 to 17.7.1776
    January + February + March + April + May + June + July
    31 + 29 + 31 + 30 + 31 + 30 + 17 = 199 days = 28 weeks + 3 odd days

    ∴ Total number of odd days = (3 + 0) = 3
    Hence, the required day is Wednesday.



  1. What was the days of the week on 17th August , 2010 ?









  1. View Hint View Answer Discuss in Forum

    Period up to 17th August, 2010 = (2009 yr + Period from 1.1.2010 to 17.8.2010)
    Counting of odd days
    Odd day in 1600 yr = 0
    Odd days in 400 yr = 0
    9 yr = (2 leap year + 7 ordinary years) = (2 x 2 + 7 x 1 ) = 1 Week + 4 days = 4 odd days

    Number of days between 1.1.2010 to 17.8.2010
    January + February + March + April + May + June + July + August.
    = (31 + 28 + 31 + 30 + 31 + 30 + 31 + 17) days
    = 229 days = 32 weeks + 5 odd days

    Correct Option: C

    Period up to 17th August, 2010 = (2009 yr + Period from 1.1.2010 to 17.8.2010)
    Counting of odd days
    Odd day in 1600 yr = 0
    Odd days in 400 yr = 0
    9 yr = (2 leap year + 7 ordinary years) = (2 x 2 + 7 x 1 ) = 1 Week + 4 days = 4 odd days

    Number of days between 1.1.2010 to 17.8.2010
    January + February + March + April + May + June + July + August.
    = (31 + 28 + 31 + 30 + 31 + 30 + 31 + 17) days
    = 229 days = 32 weeks + 5 odd days

    Total number of odd days
    = (0 + 0 + 4 + 5) days = 9 days
    = 1 week + 2 odd days
    Hence, the required day is Tuesday.