  1. Shantanu completes 5/8 of a job in 20 days. At this rate, how many more days will he take to finish the job ?
    1. 6 days
    2. 18 days
    3. 5 days
    4. 12 days
Correct Option: D

Let the required number of days be N.
Remaining work = 1 - 5/8 = 3/8
Less work, Less days (Direct proportion)
5/8 : 3/8 : : 20 : N
⇒ N = (3/8) x 20 x 8/5
∴ N = 12 days