  1. 10 men, working 6 hours a day can complete a work in 18 days. How many hours a day must 15 men work to complete the work in 12 days?
    1. 4
    2. 3
    3. 6
    4. 8
Correct Option: C

According to given question,
10 men, can complete a work in 18 days by working 6 hours a day.
1 men, can complete a work in 18 days by working 6 x 10 hours a day.
1 men, can complete a work in 1 days by working 6 x 10 x 18 hours a day.

15 men, can complete a work in 1 days by working
6 x 10 x 18 hours a day.
15

15 men, can complete a work in 12 days by working
6 x 10 x 18 hours a day.
15 x 12

15 men, can complete a work in 12 days by working
1 x 10 x 6 hours a day.
5 x 2

15 men, can complete a work in 12 days by working
6 hours a day.
1

15 men, can complete a work in 12 days by working 6 hours a day.