4 mat-weavers can weave 4 mats in 4 days. At the same rate, how many mats would be woven by 8 mat-weavers in 8 days?
-
- 16
- 12
- 18
- 14
Correct Option: A
4 mat-weavers in 4 days can weave 4 mats.
1 mat-weavers in 4 days can weave 4 / 4 mats.
1 mat-weavers in 1 days can weave 4 / 4 x 4 mats.
8 mat-weavers in 1 days can weave 4 x 8 / 4 x 4 mats.
8 mat-weavers in 8 days can weave 4 x 8 x 8 / 4 x 4 mats.
8 mat-weavers in 8 days can weave 4 x 2 x 2 mats.
8 mat-weavers in 8 days can weave 16 mats.