  1. The concept of ‘Dry Garden’ is associated with









  1. View Hint View Answer Discuss in Forum

    The Japanese rock garden or "dry landscape" garden, often called a zen garden, creates a miniature stylized landscape through carefully composed arrangements of rocks, water features, moss, pruned trees and bushes, and uses gravel or sand that is raked to represent ripples in water.

    Correct Option: A

    The Japanese rock garden or "dry landscape" garden, often called a zen garden, creates a miniature stylized landscape through carefully composed arrangements of rocks, water features, moss, pruned trees and bushes, and uses gravel or sand that is raked to represent ripples in water.


  1. ‘Mushroom Column’ is a typical feature of









  1. View Hint View Answer Discuss in Forum

    ‘Mushroom Column' is a typical feature of Johnson Wax Building whose Architect is Frank Lloyd Wright.

    Correct Option: D

    ‘Mushroom Column' is a typical feature of Johnson Wax Building whose Architect is Frank Lloyd Wright.



  1. ‘Dharahara’ refers to









  1. View Hint View Answer Discuss in Forum

    It is Heritage tower located at Kathmandu, Nepal.

    Correct Option: C

    It is Heritage tower located at Kathmandu, Nepal.


  1. Two design options of a business building on a 10.0 hectare site are being compared for built up area. Floor to floor height of Option A is 3.6 m and that of Option B is 4.5 m. If the maximum allowable building height is 45 m with same ground coverage for both options, the additional built up area achievable in Option A over Option B is______percent.









  1. View Hint View Answer Discuss in Forum

    20 to 20

    Correct Option: A

    20 to 20



  1. In India, for 1.0 cum of M-20 grade concrete, the number of cement bags required is ________ (up to two decimal places).









  1. View Hint View Answer Discuss in Forum

    5 to 9
    Composition of M20 grade of concrete is 1:1.5:3 (Cement: Sand : Aggregate) (Total 5.5) i.e. 5.5-unit volume of M20 grade of concrete contains 1-unit volume of cement.
    Thus, 1 cu.m. Volume of M20 grade of concrete contains 0.19 cu.m, volume of cement. Wet concrete hardens after some time. Generally, volume of d-y Concrete = 1.54 to 1.57 times Volume of wet concrete
    Thus, for 1 cu.m. Volume of wet M20 grade of concrete contains, 0.19 × 1.5 = 0.285 cu.m, volume of cement. 1 cu.m. of cement = 1440 kg.
    Thus, 0.285 cu.m, of cement = 410 kg. The standard weight of each cement bag = 50 kg.
    Thus, for 410 kg of cement, the number of 50 kg cement bags required = 410 50 = 8.208= 8 bags

    Correct Option: A

    5 to 9
    Composition of M20 grade of concrete is 1:1.5:3 (Cement: Sand : Aggregate) (Total 5.5) i.e. 5.5-unit volume of M20 grade of concrete contains 1-unit volume of cement.
    Thus, 1 cu.m. Volume of M20 grade of concrete contains 0.19 cu.m, volume of cement. Wet concrete hardens after some time. Generally, volume of d-y Concrete = 1.54 to 1.57 times Volume of wet concrete
    Thus, for 1 cu.m. Volume of wet M20 grade of concrete contains, 0.19 × 1.5 = 0.285 cu.m, volume of cement. 1 cu.m. of cement = 1440 kg.
    Thus, 0.285 cu.m, of cement = 410 kg. The standard weight of each cement bag = 50 kg.
    Thus, for 410 kg of cement, the number of 50 kg cement bags required = 410 50 = 8.208= 8 bags