  1. The critical path for the project is
    1. a-b-e-g-h
    2. a-c-g-h
    3. a-d-f-h
    4. a-b-c-f-h
Correct Option: C


Various path are
A B E G H – 17 days
A C G H – 16 days
A D F H – 18 days;
Hence A D F H is critical path