  1. The project activities, precedence relationships and durations are described in the table. The critical path of the project is
    1. P–R–T–V
    2. Q–S–T–V
    3. P–R–U–W
    4. Q–S–U–W
Correct Option: D


Path QSUW = Q + S + U + W
= 4 + 5 + 5 +10 = 24 days.