Home » Industrial Engineering » Industrial Engineering Miscellaneous » Question

Industrial Engineering Miscellaneous

Industrial Engineering

  1. A manufacturing shop processes sheet metal jobs, wherein each job must pass through two machines (M1 and M2, in that order). The processing time (in hours) for these jobs is

    The optimal make-span (in hours) of the shop is
    1. 120
    2. 115
    3. 109
    4. 79
Correct Option: B

Using Johnson’s algorithm



Your comments will be displayed only after manual approval.