  1. The table gives details of an assembly line.

    What is the line efficiency of the assembly line?
    1. 70%
    2. 75%
    3. 80%
    4. 85%
Correct Option: C

Line efficiency

=
Total time used
× 100
Number of work stations×Cycle time

=
48
× 100 = 80%
6 × 10