  1. The arc lengths of a directed graph of a project are as shown in the figure. The shortest path length from node 1 to node 6 is________.

    1. 7
    2. 6
    3. 5
    4. 8
Correct Option: A

= 1 – 2 – 5 – 4 – 6 = 2 + 2 + 1 + 2 = 7