  1. A project starts with activity A and ends with activity F. The precedence relation and durations of the activities are as per the following table:

    The minimum project completion time (in days) is ________ .
    1. 24 days
    2. 23 days
    3. 21 days
    4. 22 days
Correct Option: A


Minimum Project completion (14 Days)
= a – c – e – f
= 4 + 7 + 4 + 9
= 24 days