A project starts with activity A and ends with activity F. The precedence relation and durations of the activities are as per the following table:
The minimum project completion time (in days) is ________ .
-
- 24 days
- 23 days
- 21 days
- 22 days
Correct Option: A
Minimum Project completion (14 Days)
= a – c – e – f
= 4 + 7 + 4 + 9
= 24 days