  1. The activities of a project, their duration and the precedence relationships are given in the table. For example, in a precedence relationship “ X < Y, Z” means t hat X is pr edecessor of activities Y and Z. The time to complete the activities along the critical path is ____ weeks.
    1. 25
    2. 17
    3. 21
    4. 23
Correct Option: D


Critical path: A → B → F → I
Time to complete the activities along the critical path = 23 weeks