The activities of a project, their duration and the precedence relationships are given in the table. For example, in a precedence relationship “ X < Y, Z” means t hat X is pr edecessor of activities Y and Z. The time to complete the activities along the critical path is ____ weeks.
-
- 25
- 17
- 21
- 23
Correct Option: D
Critical path: A → B → F → I
Time to complete the activities along the critical path = 23 weeks