Industrial Engineering

  1. A set of 5 jobs is to be processed on a single machine. The processing time (in days) is given in the table below. The holding cost for each job is Rs K per day.

    1. T-S-Q-R-P
    2. P-R-S-Q-T
    3. T-R-S-Q- P
    4. P-Q-R-S-T
Correct Option: A


= T – S – Q – R – P