  1. Six jobs arrived in a sequence as given below:

    Average flow time (in days) for the above jobs using Shortest Processing Time rule is
    1. 20.83
    2. 23.16
    3. 125.00
    4. 139.00
Correct Option: A

Jobs using

Average time flow =
4 + 9 + 15 + 23 + 32 + 12
6

= 20.83