Water requirements miscellaneous
- Aeration of water is done to remove
-
View Hint View Answer Discuss in Forum
Duration of operation of slow sand filter is 1-3 months.
Correct Option: D
Duration of operation of slow sand filter is 1-3 months.
- The disinfection efficiency of chlorine in water treatment.
-
View Hint View Answer Discuss in Forum
NA
Correct Option: D
NA
- Use of coagulants such as alum
-
View Hint View Answer Discuss in Forum
NA
Correct Option: A
NA
- 16 MLD of water is flowing through a 2.5 km long pipe of diameter 45 cm. The chlorine at the rate of 32 kg/d is applied at the entry of this pipe so that disinfected water is obtained at the exit. There is a proposal to increase the flow through this pipe to 22 MLD from 16 MLD. Assume the dilution coefficient, n = 1. The minimum amount of chlorine (in kg per day) to be applied to achieve the same degree of disinfection for the enhanced flow is
-
View Hint View Answer Discuss in Forum
We know, tcn = k
where C is the concentration and n is the direction coeff.
t is time required to kill organism.
Here n = 1t = L V
where, L = length of pipe
V = velocity of flowt = L = L V Q/A t = LA Q L = W Q
where, W = weight of disinfectant/day
Q = discharge/day
t1Cn1 = t2Cn2LA × w1 = LA × W2 × Q1 Q1 Q2 Q2 ∴ W2 = Q²2 × W1 Q²1 = 22 ² × 32 = 60.5 kg/d 16 Correct Option: A
We know, tcn = k
where C is the concentration and n is the direction coeff.
t is time required to kill organism.
Here n = 1t = L V
where, L = length of pipe
V = velocity of flowt = L = L V Q/A t = LA Q L = W Q
where, W = weight of disinfectant/day
Q = discharge/day
t1Cn1 = t2Cn2LA × w1 = LA × W2 × Q1 Q1 Q2 Q2 ∴ W2 = Q²2 × W1 Q²1 = 22 ² × 32 = 60.5 kg/d 16
- A water treatment plant is designed to treat 1 m³/s of raw water. It has 14 sand filters. Surface area of each filter is 50 m². What is the loading rate (in (m³/days.m²)) with two filters out of service for routine backwashing?
-
View Hint View Answer Discuss in Forum
Hydraulic loading rate = Q A = 1 m³/sec.m² 12 × 50 = 1 × 24 × 60 × 60 m³/day.m² 12 × 50
= 144 m³/day.m²Correct Option: D
Hydraulic loading rate = Q A = 1 m³/sec.m² 12 × 50 = 1 × 24 × 60 × 60 m³/day.m² 12 × 50
= 144 m³/day.m²