  1. Following data refers to the jobs (P, Q, R, S) which have arrived at a machine for scheduling. The shortest possible average flow time is ____ days.
    JobProcessing Time (days)
    P15
    Q9
    R 22
    S12
    1. 31
    2. 32
    3. 33
    4. 30
Correct Option: A


Near flow time =
Σ ci
=
124
= 31
44