Direction: Consider a PERT network for a project involving six tasks (a to f)

  1. The expected completion time of the project is
    1. 238 days
    2. 224 days
    3. 171 days
    4. 155 days
Correct Option: D


⇒ a – c – e – f
⇒ 30 + 60 + 45 + 20 = 155 days