Home » Industrial Engineering » Industrial Engineering Miscellaneous » Question

Industrial Engineering Miscellaneous

Industrial Engineering

  1. For planning the procurement or production of dependent demand items, the technique most suited is
    1. MRP
    2. IMF
    3. Supply
    4. All of above
Correct Option: A

MRP