An electronic equipment manufacturer has decided to add a component subassembly operation that can produce 80 units during a regular 8-hour shift. This operation consists of three activities as below
For line balancing the number of work stations required for the activities M, E and T would respectively be
-
- 2, 3, 1
- 3, 2, 1
- 2, 4, 2
- 2, 1,3
Correct Option: A
Number of units produce in a day = so units working hour in a day = 8 hours
Time taken to produce 1 unit = | × 60 = 6 min | |
80 |
T = 6 min

Number of work station are the whole number more the function.
So no of work station required for the activities, M, E & T would be 2, 3, 4, 1