  1. An electronic equipment manufacturer has decided to add a component subassembly operation that can produce 80 units during a regular 8-hour shift. This operation consists of three activities as below

    For line balancing the number of work stations required for the activities M, E and T would respectively be
    1. 2, 3, 1
    2. 3, 2, 1
    3. 2, 4, 2
    4. 2, 1,3
Correct Option: A

Number of units produce in a day = so units working hour in a day = 8 hours

Time taken to produce 1 unit =
8
× 60 = 6 min
80

T = 6 min

Number of work station are the whole number more the function.
So no of work station required for the activities, M, E & T would be 2, 3, 4, 1