  1. A project consists of 14 activities, A to N. The duration of these activities (in days) are shown in brackets on the network diagram. The latest finish time (in days) for node 10 is_________.
    1. 12 days
    2. 16 days
    3. 14 days
    4. 16 days
Correct Option: C


(LFT) for node 10 = 14 days