The annual requirement of rivets at a ship manufacturing company is 2000 unit. The rivets are supplied in units of 1 kg costing Rs. 25 each. The costs Rs. 100 to place an order and the annual cost of carrying one unit is 9% of its purchase cost, the cycle length of the order (in days) will be ______.
-
- 76.9457 days
- 75.9457 days
- 73.9457 days
- 74.9457 days
Correct Option: A
D = 2000 unit
C = Rs 25
CO = Rs 100
Ch = | × 25 = 2.25 | 100 |

= 421.637
No of orders per year
N = | Q* |
= | 421.637 |
⇒ 4.7434
Cycle length of order
⇒ | N |
⇒ | ⇒ 76.9457 days | 4.474 |