Direction: Read the following information and answer the questions
given below:
(i) P, Q, R, S and T finished the work, working from Monday to Saturday, one of the days being a holiday, each working overtime only on one of the days.
(ii) R and T did not work overtime on the first day
(iii) Q worked overtime the next day after the holiday
(iv) The overtime work done on the previous day of the holiday was by R
(v) There was a two days’ gap between the days on which P and Q worked overtime.
(vi) P worked overtime the next day of the overtime day of S.
-
How many days’ gap was there between the days on which P and T worked overtime?
-
- Three
- Two
- One
- Cannot be determined
- None of these
- Three
Correct Option: A
According to question , we can say that
P, Q, R, S and T finished the work, working from Monday to Saturday, one of the days being a holiday, each working overtime only on one of the days.
There was a two days’ gap between the days on which P and Q worked overtime.
P worked overtime the next day of the overtime day of S.
Therefore , required answer will be three days .