Direction: Study the following information to answer the given questions:
Ajay would do five tasks: A, B, C, D and E, stating at 9 am in the morning. A is the first task and takes two hours. B can be done after A is completed and requires 1 hour. Work on C which would take 1 hour can start only after A and B are complete. Ajay can do task D along with B and C and would take 3 hours for that. Activity E with duration of 1 hour can start on completion of A, B, C and D.
-
What is the earliest time when Ajay can complete all tasks?
-
- 4 pm
- 3 pm
- 2 pm
- 1 pm
Correct Option: B
From the solution of previous questions Ajay completed tasks at 3 pm.