Direction: The following pie-chart shows the sources of funds (In $ billion) to be collected by the National Highways Authority of India (NHAI) for its Phase II projects. Study the pie-chart and answer the following Three questions :

  1. If the toll is to be collected through an outsourced agency by allowing a maximum 10% commission, how much amount should be permitted to be collected by the outsourced agency, so that the project is supported with $ 4,910 billion?
    1. $ 6,213 billion
    2. $ 5,827 billion
    3. $ 5,401 billion
    4. $ 5,316 billion
Correct Option: C

If the amount permitted be $ x then,

X ×
100
= 4910
110

⇒ X =
4910 × 110
= $ 5401 billion
100