  1. A CPM network of a construction project is given in the figure below. The activity durations are mentioned in weeks. The project completion time in weeks will be _____________









  1. View Hint View Answer Discuss in Forum

    18 to 18

    Correct Option: C

    18 to 18


  1. Match the instruments in Group-I with the corresponding usage in Group-II
    Group IGroup II
    P. Pyranometer1. Shadow analysis
    Q. Heliodon2. Seismic intensity
    R. Total Station3. Wind velocity
    S. Anemometer4. Solar radiation
    5. Land survey









  1. View Hint View Answer Discuss in Forum

    P-4, Q-1, R-5, S-3

    Correct Option: C

    P-4, Q-1, R-5, S-3



  1. Associate the systems in Gr oup-I with their applications in Group-II
    Group IGroup II
    P. Nisargruna1. Renewable energy generation
    Q. Vortex-DEWAT2. Ground water recharge
    R. Swale3. Solid waste management
    S. Swale4. Desalination
    5. Waste water treatment









  1. View Hint View Answer Discuss in Forum

    P-3, Q-5, R-2, S-1

    Correct Option: C

    P-3, Q-5, R-2, S-1