  1. A CPM network of a construction project is given in the figure below. The activity durations are mentioned in weeks. The project completion time in weeks will be _____________
    1. 14 : 14
    2. 16 : 16
    3. 18 : 18
    4. 20 : 20
Correct Option: C

18 to 18