Download
App
Academic Resource
Aptitude
Data Interpretation
Verbal Reasoning
Non Verbal Reasoning
Verbal Ability
Programming
General Knowledge
Puzzle
Engineering
Computer Engineering
Electronics and Communication
Electrical Engineering
Mechanical Engineering
Civil Engineering
Biotechnology
Architecture & Planning
Online Test
Aptitude Test
Data Interpretation Test
Verbal Reasoning Test
Non Verbal Reasoning Test
Verbal Ability Test
Exams
More
Full Forms
हिंदी
Home
»
Architecture and Planning Miscellaneous
»
Architecture and Planning Miscellaneous-topic
» Question
Architecture and Planning Miscellaneous-topic
Easy Questions
Moderate Questions
Difficult Questions
Architecture and Planning Miscellaneous
Architecture and Planning Miscellaneous-topic
A CPM network of a construction project is given in the figure below. The activity durations are mentioned in weeks. The project completion time in weeks will be _____________
14 : 14
16 : 16
18 : 18
20 : 20
Correct Option:
C
18 to 18