In Critical Path Method (CPM) for time scheduling, ‘for war d pass calculat i on’ is car r ied out for determining
-
- Late start and early finish time
- Early start and early finish time
- Late start and late finish time
- Early start and late finish time
Correct Option: B
‘Forward pass calculation' is carried out for determining Early start and early finish time.
(a) Forward Pass Computations : (EST)ij = Ei.
(EFT)ij = Maximum of [(EST)ij + tEij]∀ i - j leading into event j
(b) Backward Pas Computations :
(LFT)ij = Ei.
(EFT)ij = Maximum of [(LFT)ij + tijE]∀i - j emanating from node i