A borrow pit soil has a dry density of 17 kN/m3. How many cubic meters of this soil will be required to construct an embankment of 100 m3 volume with a dry density of 16 kN/ m3
-
- 94 m3
- 106 m3
- 100 m3
- 90 m3
Correct Option: A
Borrow pit volume be v1
Embankment volume bc V2 = 100 m3
= | ||||
V2 | γd1 |
⇒ | = | |||
100 | 17 |
⇒ V1 = 94.11 m3