  1. Identical surcharges are placed at ground surface at sites X and Y, with soil conditions shown alongside and water table at ground surface. The silty clay layres at X and Y are identical. The thin sand layer at Y is continouous and freedraining with a very large discharge capacity. If primary consolidation at X is estimated to complete in 36 months, what would be the corresponding time for compeltion of primary cosnolidation at Y?
    1. 2.25 months
    2. 4.5 months
    3. 9 months
    4. 36 months
Correct Option: C

Time factor,

Tv =
Cvt
d2

∴ t ∝ d2
At site X, d1 = 10 m and t1 = 36 months
At site Y, d2 = 5 m and t2 =?
t1
=
d12
t2d22

∴ t2 = 36 × 52
∴ t2 =
36 × 52
= 9 months
102