The direct runoff hydrograph of a storm obtained from a catchment is triangular in shape and has a base period of 80 hours. The peak flow rate is 30 m³/sec and catchment area is 86.4 km². The rainfall excess that has resulted the above hydrograph is
-
- 5 cm
- 8 cm
- 10 cm
- 16 cm
Correct Option: A
Volume of run off = Area of hydrograph
= | × 30 × (80 × 60 × 60) | |
2 |
= 4320000 m³/s
Area of catchment = 86.4 km² = 86.4 × 106 m²
Rainfall excess = run off
= | ||
Area of catchment |
= | = 0.05 m | |
86.4 × 106 |