  1. The height of the down sprue is 175 mm and its CS are at the base is 200 mm². The CS area of the horizontal runner is also 200 mm². Assuming no losses, indicate the correct choice for-the time (second) required to fill a mould cavity of volume 106mm3. (Use g = 10 m/s²)
    1. 2.67
    2. 8.45
    3. 26.7
    4. 84.50
Correct Option: C

Vs = √2 × 10 × 175 × 10−3
= 1870 mm/s
Pouring time

t =
106
200 × 1870

t = 2.67 m/s