Home » Architecture and Planning Miscellaneous » Architecture and Planning Miscellaneous-topic » Question

Architecture and Planning Miscellaneous-topic

Architecture and Planning Miscellaneous

  1. In the given project network diagram, the total slack for job A in days would be _______.
    1. 0
    2. 1
    3. 2
    4. 3
Correct Option: B

For activity F to start, activities (B + C) & (A + E) must been finished.
As activities (B + C) takes 6 days to finish to start the activity F.
Activities (A + E) takes 5 days to finish to start the activity F.
Which means that activity A can be delayed by 1 day without affecting the start of activity F.
The delay by one day is actually slack.