In the given project network diagram, the total slack for job A in days would be _______.
-
- 0
- 1
- 2
- 3
Correct Option: B
For activity F to start, activities (B + C) & (A + E) must been finished.
As activities (B + C) takes 6 days to finish to start the activity F.
Activities (A + E) takes 5 days to finish to start the activity F.
Which means that activity A can be delayed by 1 day without affecting the start of activity F.
The delay by one day is actually slack.